PK0-005: Project+ Practice Exam — PK0-005: Project+

1. The question bank is cloud-based and updates automatically, with no need for re-acquisition.

2. Available in Chinese and English. It supports online practice, mock exams and PDF downloads.

3. You can practice questions via mini-program or desktop web page. The service is valid for one year.

4. For inquiries, please contact customer service via WeChat, WhatsApp or Line.

Exam information

PK0-005: CompTIA Project+

-Exam Overview: Suitable for entry-level project managers. It validates fundamental capabilities throughout project initiation, planning, execution, monitoring and closure.

-Key Specifications:

 - Exam Duration: 90 minutes

 - Number of Questions: Up to 75 (Single choice, multiple choice, scenario-based questions)

 - Total Score / Passing Score: 900 / 710

 - Exam Fee: Approximately $392 USD

 - Supported Languages: English, Japanese, etc.

 - Official Registration Link: https://www.comptia.org/certifications/project

-Core Topics:

 - Project lifecycle management

 - Stakeholder management, communication and risk management

 - Project documentation, change management and closure procedures

Sample questions

PK0-005: Project+ · Q1
Topic 1 Question #1 DRAG DROP - During a gate review meeting, the deliverable was rejected by the customer. Review the dashboard. Part 1: Drag and drop each task, placing them in the correct order based on the project change control process. Part 2: Select the proper document(s) to be updated. " target="_blank" rel="nofollow noopener">https://img.examtopics.com/pk0-005/image1.png">
  • A.
    错误
  • B.
    正确

Answer: B

" target="_blank" rel="nofollow noopener">https://img.examtopics.com/pk0-005/image2.png"> " target="_blank" rel="nofollow noopener">https://img.examtopics.com/pk0-005/image3.png">
PK0-005: Project+ · Q2
Topic 1 Question #2 A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.)
  • A.
    Train users on the proper use of the system.
  • B.
    Escalate the issue to the CCB.
  • C.
    Hold sessions to understand user challenges.
  • D.
    Track system usage and report user activity.
  • E.
    Log the issue in the project risk register.
  • F.
    Create a memorandum of acceptable use.

Answer: CE

This question aligns with core CompTIA Project+ PK0-005 domains including stakeholder engagement and risk management. The scenario requires two complementary steps: first, identify the root cause of the sales team's reluctance to understand adoption barriers, and second, formally manage the associated risk to project success. Holding user challenge sessions (Option C) directly facilitates feedback collection from the impacted stakeholder group to surface specific concerns driving resistance, which is a required first step to address adoption gaps. Logging the issue in the project risk register (Option E) formalizes the identified risk to project objectives, ensures it is assigned an owner, monitored, and paired with appropriate response plans to drive organizational acceptance, which adheres to PK0-005 risk management requirements. Option Analysis: A. Incorrect. Training is a potential corrective action after root causes of reluctance are identified, but it does not address the question's requirement to first understand adoption issues. Per PK0-005 guidance, solutions should not be implemented before the source of stakeholder resistance is confirmed, so this is a premature action for the stated goals. B. Incorrect. The Change Control Board (CCB) is only responsible for reviewing and approving baseline change requests per PK0-005 change management processes. Stakeholder adoption reluctance is a risk and stakeholder engagement issue, not a change request, so escalation to the CCB is not appropriate here. C. Correct. PK0-005 stakeholder engagement domain guidance specifies that facilitated feedback sessions with resistant end users are the standard method to identify root causes of resistance to new deliverables, which directly fulfills the question's requirement to understand adoption issues. D. Incorrect. Tracking system usage only measures adoption levels post-implementation, it does not provide insight into why users are reluctant or support efforts to gain organizational acceptance, so it does not meet the scenario's stated objectives. E. Correct. Per PK0-005 risk management processes, any identified event that could jeopardize project success must be logged in the risk register to enable formal tracking, analysis, and response planning. This step ensures the adoption barrier is prioritized and addressed to gain organizational acceptance. F. Incorrect. A memorandum of acceptable use is a governance document that enforces system usage rules, which would likely increase stakeholder resistance rather than address underlying concerns, and it does not support the goal of understanding existing adoption issues. Key Concepts: 1. Stakeholder Engagement: A core PK0-005 domain that covers processes to proactively communicate with and gather feedback from impacted stakeholders to identify and resolve resistance to project deliverables. 2. Risk Identification and Tracking: A component of the PK0-005 risk management domain that requires all identified risks to project objectives are documented in the risk register for ongoing monitoring and response execution. 3. User Adoption Root Cause Analysis: A required implementation activity for IT projects per PK0-005 guidance, which mandates that barriers to end user adoption are diagnosed before corrective actions are implemented to ensure project value is realized. References: CompTIA Project+ PK0-005 Exam Objectives, CompTIA Project+ Certification Overview, https://www.comptia.org/certifications/project
PK0-005: Project+ · Q3
Topic 1 Question #3 Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?
  • A.
    Daily stand-up
  • B.
    Project momentum
  • C.
    Performance feedback
  • D.
    Meeting minutes

Answer: C

The scenario describes a post-release stakeholder survey focused on identifying opportunity areas for the project team, a core closing phase activity aligned with CompTIA Project+ PK0-005 domain requirements. The survey captures stakeholder perceptions of the team's performance, communication effectiveness, deliverable alignment with expectations, and specific gaps to address. These results provide factual, stakeholder-centric insights that directly serve as input for performance feedback, as they enable the project manager to deliver balanced, actionable feedback that recognizes team strengths and targets documented improvement areas for current and future projects. This aligns with PK0-005 requirements to leverage stakeholder input to evaluate team performance and drive continuous improvement. Option Analysis: A. Incorrect. Daily stand-ups are short, execution-phase sync meetings focused on immediate task progress, active blockers, and near-term work plans. Their scope is limited to ongoing, in-progress work, so they do not use post-release, broad stakeholder feedback as an input. B. Incorrect. Project momentum is an intangible measure of a project's forward progress and team engagement during active execution, not a structured process or artifact that accepts survey results as an input. Post-release surveys are collected after core project execution is complete, so they do not impact momentum for the completed project. C. Correct. Performance feedback for project teams relies on multiple objective input sources, including stakeholder satisfaction data, to ensure feedback is balanced and actionable. The post-release survey results directly capture stakeholder perspectives on the team's work, making them a valid input for feedback sessions that highlight successes and opportunity areas for the team. This aligns with PK0-005 resource and stakeholder management domain objectives. D. Incorrect. Meeting minutes are a documented output of meetings, used to record discussions, action items, and decisions. While survey results may be discussed during a meeting and referenced in associated minutes, the minutes themselves do not use the survey as a formal input, as they are simply a record of meeting activities, not a process that consumes survey data to produce an output. Key Concepts: 1. Post-Release Stakeholder Feedback: Per PK0-005, collecting stakeholder feedback after deliverable deployment is a mandatory closing phase activity used to evaluate project success, identify gaps, and inform process and performance improvements for future work. 2. Team Performance Evaluation Inputs: PK0-005 emphasizes that performance feedback for teams must be based on multiple data points, including stakeholder feedback, task delivery metrics, and project outcomes, to ensure feedback is objective and actionable. 3. Continuous Improvement Cycles: Stakeholder survey results identifying team opportunity areas are a core input to continuous improvement processes, which are required for both individual team development and organizational project management maturity per Project+ standards. References: CompTIA Project+ PK0-005 Exam Objectives, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – 6th Edition, https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
PK0-005: Project+ · Q4
Topic 1 Question #4 Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
  • A.
    Evaluating the project
  • B.
    Releasing the resources
  • C.
    Closing the contracts
  • D.
    Reconciling the budget

Answer: D

The project triple constraint, also called the iron triangle, consists of three interdependent core project constraints: cost (approved budget), scope (required deliverables), and schedule (project timeline). The closing phase of a project requires validating that the project adhered to all three constraints as part of formal finalization. Reconciling the budget directly addresses the cost component of the triple constraint, and also provides data that links to scope and schedule performance, as cost variances are often tied to unapproved scope changes or schedule delays. This activity involves comparing actual project expenditures against the approved budget baseline, documenting variances and their root causes, resolving all outstanding financial obligations, and confirming no unaccounted costs remain. This formal validation of cost performance directly supports tracking and confirming adherence to the triple constraint during project closing, as required by the question. Option Analysis: A. Evaluating the project is incorrect. While project evaluation is a general closing phase activity, it is a broad assessment of overall project success, stakeholder satisfaction, and deliverable alignment with business objectives, rather than a targeted activity focused specifically on supporting the triple constraint framework. It does not directly validate performance against the three core constraints of the triple constraint. B. Releasing the resources is incorrect. Releasing project team members, physical assets, and tools is an administrative closing task focused on reallocating resources to other work after project completion. It has no direct tie to measuring or validating performance against the triple constraint, so it does not meet the question requirement. C. Closing the contracts is incorrect. Closing contracts is a procurement-specific closing activity that only finalizes vendor agreements, accepts vendor deliverables, and settles vendor payments. It only addresses a subset of total project costs, rather than the full project budget that defines the cost component of the triple constraint, so it does not support the full triple constraint framework. D. Reconciling the budget is correct. This activity directly validates adherence to the cost constraint, one of the three core elements of the triple constraint. It also captures cost variance data that enables analysis of how scope and schedule changes impacted project costs, supporting comprehensive review of all triple constraint performance during closing. It is explicitly aligned with the question requirement of a closing phase activity that supports the triple constraint. Key Concepts: 1. Project Triple Constraint: A core project management framework that defines three interdependent constraints (cost, scope, schedule) that govern every project. Changes to any one constraint require adjustments to one or both of the other constraints to maintain project performance, and performance against all three is formally validated during the closing phase. 2. Project Closing Phase: The final phase of the project lifecycle, which includes formal acceptance of final deliverables, settlement of all financial and contractual obligations, documentation of lessons learned, release of resources, and formal sign-off to mark project completion. 3. Budget Reconciliation: A closing phase financial activity that matches all actual project expenditures against the approved budget baseline, documents variances and their root causes, resolves outstanding invoices, and finalizes all financial records to confirm the project was delivered within approved cost limits. References: CompTIA Project+ (PK0-005) Exam Objectives, Project Management Institute (PMI) Closing Process Group Overview
PK0-005: Project+ · Q5
Topic 1 Question #5 During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?
  • A.
    Ishikawa diagram
  • B.
    Scatter diagram
  • C.
    Pareto chart
  • D.
    Decision tree

Answer: C

The scenario describes a quality analysis process where causes of quality issues have already been identified, and the project manager needs to prioritize these causes to identify which are most important to address. This requirement aligns with the quality management domain content tested on the PK0-005 CompTIA Project+ exam, which covers appropriate tool selection for quality control and improvement activities. The correct tool for this use case is the Pareto chart, as it leverages the 80/20 Pareto principle to rank causes by their impact, allowing the project team to focus on the small subset of causes that drive the majority of quality issues, maximizing the efficiency of quality improvement efforts. Option Analysis: A. Incorrect. The Ishikawa (fishbone) diagram is a root cause identification tool used to brainstorm and map potential causes of a specific quality problem before causes are confirmed. It is not designed to prioritize already identified causes by importance, so it does not meet the requirements of the scenario. B. Incorrect. A scatter diagram is used to measure and display the correlation between two continuous variables, such as the relationship between material thickness and product failure rate. It does not rank multiple identified causes of issues by their relative importance, so it is not appropriate for this use case. C. Correct. A Pareto chart is a sorted bar chart that organizes identified causes of quality issues in descending order based on the frequency, cost, or overall impact of the issues they generate. It applies the Pareto principle to highlight the small set of high-impact causes (the vital few) that are responsible for most quality problems, directly supporting the requirement to identify the most important causes. D. Incorrect. A decision tree is a quantitative decision analysis tool used to calculate the expected value of different potential courses of action under uncertain conditions. It is not designed for prioritizing root causes of quality issues, so it does not fit the scenario parameters. Key Concepts: 1. Pareto Principle (80/20 Rule): A core quality management concept tested on PK0-005 that states roughly 80% of project defects or issues are caused by just 20% of root causes, forming the foundation for targeted quality improvement prioritization. 2. Quality Tool Use Case Differentiation: CompTIA Project+ requires candidates to distinguish between common quality management tools, their core functions, and appropriate application across quality planning, assurance, and control processes. 3. Root Cause Prioritization: A key quality management activity where confirmed root causes are ranked by impact to ensure limited project resources are allocated to resolve the highest-value quality issues first, delivering the fastest improvement to overall project quality. References: CompTIA Project+ (PK0-005) Exam Objectives, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

FAQ

How many practice questions are available for PK0-005: Project+?

This question bank includes 619 PK0-005: Project+ practice questions covering single and multiple choice, each with answers and explanations.

Are PK0-005: Project+ practice questions available in Chinese and English?

Yes, PK0-005: Project+ practice questions are provided in both Chinese and English.

Can I try PK0-005: Project+ practice questions for free?

Yes. Free sample questions are available on this page, and the full question bank is available after signing up on Zhangxuetu.